3.2 Test Monitoring and Control Process
This process is used to validate if the testing progress is according to the Test Plan and the organizational specifications. If not, activities will be initiated to correct or compensate for the resultant variances.
The process is normally applied so it manage the whole test project, but can of course also be applied on the different test levels (phases) (eg. System or/and Acceptance testing). If applied as part of the monitoring and control of the testing for the whole test project then it will interact directly with the test management processes being used to manage the individual test levels and test types of the project.
Purpose:
Determine whether testing progresses in accordance with the Test Plan and with organizational test specifications. Initiates control actions as necessary and identify necessary updates to the Test Plan
Inputs to activities in this process may include:
- Test Plans
- Product documentation
- Organizational Test Policy
- Organizational Test Strategy
- Control Directives (from a higher level process)
- Measures from the Test Process being managed
Expected outcome of Test Monitoring and Control Process implementation:
- The means of collecting suitable measures to monitor test progress and changing risk are set up
- Progress against the test plan is monitored
- New and changed test-related risks are identified, analyzed and necessary action(s) invoked
- Necessary control actions are identified
- Necessary control actions are communicated to the relevant stakeholders
- The decision to stop testing is approved
- Test progress and changes to the risks are reported to stakeholders
- Information items to be produced:
- Test status reports
- Test plan updates
- Control directives
- Project and product risk information
3.2.1 Graphic overview of the Test Monitoring and Control Process:
Figure: Test Monitoring and Control Process. Important to understand that in practice some of the activities are carried out iteratively. This means that you might have to revisit some of the activities multiple times
The Test Manager or the person(s) responsible for test monitoring and control shall implement the following activities and tasks in accordance with applicable organization policies and procedures with respect to the Test Monitoring and Control Process.
# | Activity | Tasks |
TMC1 |
Set-up |
|
TMC2 |
Monitor |
|
TMC3 |
Control |
|
TMC4 |
Report |
|